Critical path
Prev
Next

Critical path

A path is a series of connected tasks. In project management, a critical path is the sequence of project network terminal elements with the longest overall duration, determining the shortest time to complete the project.

The duration of the critical path determines the duration of the entire project. Any delay of a terminal element on the critical path directly impacts the planned project completion date (i.e. there is no float on the critical path). For example, if a task on the critical path is delayed by one day, then the entire project will be delayed by one day (unless another task on the critical path can be accelerated by one day).

A project can have several, parallel critical paths. An additional parallel path through the network with the total duration just shorter than the critical path is called a sub-critical path.

Originally, the critical path method considered only logical dependencies among terminal elements. A related concept is the critical chain, which adds resource dependencies.

The critical path method was invented by the DuPont corporation.

Prev
Next
Home


Would you like to comment or contribute an update to this page?
Send feedback to the TDE Development Team